Offer of Possession without completion certificate is not valid Supreme Court orders full refund of amount paid by consumer with 9% interest p.a. and Rs. 15 lakh compensation.

Judgment dated 6th September 2024

Cause title : DHARMENDRA SHARMA. vs AGRA DEVELOPMENT AUTHORITY

Case No: Civil Appeal Nos. 2809-2810 of 2024

A Bench of Supreme Court Judges Hon'ble Mr. Justice Vikram Nath and Hon'ble Mr. Prasanna Balachandra Varale partly allowed the appeal filed by the Petitioner against the final Judgment passed by the National Consumer Disputes Redressal Commission.  The only issue in the matter was as to whether the possession as offered on 04.12.2014 should be taken as a valid offer of possession even if there was no completion certificate and also whether the firefighting clearance certificate was available with the ADA or not.

The Hon'ble Supreme Court held that
"...On the other hand, the ADA, despite making an offer of possession in 2014, did not fulfil its statutory obligations by providing the requisite completion certificate and firefighting clearance certificate, both of which are essential for a valid and lawful offer of possession. The absence of these documents, which were also not furnished before the NCDRC, unquestionably vitiates the offer of possession made by the ADA."

Facts of the case are:

The appellant -Dharmendra Sharma had applied for allotment and purchase of an apartment (residential flat) in the category of Super Deluxe 2 on 28.07.2011 and had deposited the booking amount of Rs.4,60,000/- along with the application. This application was submitted pursuant to an advertisement issued by the ADA for a group housing project lodged in the name of ADA Heights, Taj Nagari, Phase II at Fatehabad Road, near Taj Express Way, Ring Road, Agra. The allotment was done by lottery system on 29.08.2011 whereby the appellant was allotted Flat No.DT-1/1204 which was communicated vide letter dated 19.09.2011, according to which the tentative price of the apartment was Rs.56,54,000/- which could be deposited in 24 equal quarterly instalments or could be paid in full with certain other relaxations. The appellant, opted for full payment and accordingly vide letter dated 21.10.2011, attached two cheques, one by the appellant of Rs.6.94 lakhs and the other of Rs.45 lakhs issued by the LIC Housing Finance Limited.

Possession was to be given within six months under the scheme. Upon completion of six months, the appellant requested for possession vide communication dated 03.04.2012. Apparently, the construction was not completed and, in any case, not ready for delivery of possession, as such no possession was delivered even after six months. The appellant thereafter received a communication dated 04.02.2014 offering possession subject to further payment of Rs.3,43,178/- along with non-judicial stamp paper for execution of the deed amounting to Rs.3,99,100/-.

On receipt of the said letter, the appellant visited the site as also the office of ADA on 15.02.2014. He deposited the non-judicial stamp papers as required of Rs.3,99,100/-. But after inspection of the site, he found various deficiencies in the construction which were reported to the Assistant Engineer of the ADA with the request that once the deficiencies are removed, he may be communicated for taking over possession. ADA sent reminders dated 22.09.2014 and 20/21.11.2014 for depositing the balance amount of Rs.3,82,748/-.

The appellant, on the other hand, was demanding for completion certificate. There is a further communication by the ADA dated 17.01.2018 demanding an amount of Rs.6,11,575/- and for taking possession after depositing the same and getting the deed executed. On the other hand, the appellant, vide communication dated 02.04.2018, requested for waiver of interest on the balance amount and also sought confirmation whether the flat was ready for physical possession.

It was thereafter that the appellant along with letter dated 04.06.2019, sent a cheque dated 01.06.2019 for Rs.3,43,178/- and again requested for confirmation of the date of possession. The ADA encashed the said cheque but did not inform any date for handing over possession. It looks like the appellant got the loan transferred to the State Bank of India whereupon the SBI is writing letters demanding the title deed of the apartment vide communications dated 14.03.2017, 25.06.2019 and 19.10.2019. These communications further mention that in case the title deed is not deposited, then penal interest @2% p.a. would be levied. The appellant again reiterated his earlier request for waiver of interest on balance amount vide reminder dated 18.09.2019 and again requested for confirmation whether the flat was ready for physical possession. The appellant again visited the office of ADA on 23.11.2019 and requested for completion certificate and firefighting clearance certificate, which were not provided. He again visited the site and found that the apartment was not in a habitable condition. The appellant thus proceeded to institute a complaint before the NCDRC on 10.07.2020 alleging deficiency in service as also unfair trade practice on the part of ADA.

While partly allowing the Civil Appeal the Hon'ble Supreme Court held that:

"22. This Court is of the considered view that both parties have exhibited lapses in their respective obligations. On the one hand, the appellant, despite having paid the tentative price of Rs. 56,54,000/- in 2012, failed to remit the additional amount of Rs. 3,43,178/-, as demanded by the ADA, even after being repeatedly reminded. Instead, the appellant persistently sought a waiver of the penal interest on the delayed payment, eventually settling the amount only on 04.06.2019, a significant delay that cannot be overlooked and that too without the interest component which had further accrued over a period of about five years. On the other hand, the ADA, despite making an offer of possession in 2014, did not fulfil its statutory obligations by providing the requisite completion certificate and firefighting clearance certificate, both of which are essential for a valid and lawful offer of possession. The absence of these documents, which were also not furnished before the NCDRC, unquestionably vitiates the offer of possession made by the ADA.

23. In light of the aforementioned observations and taking into account the shortcomings on the part of both the appellant and the ADA, this Court deems it appropriate to provide a compensation of Rs. 15,00,000/- (Fifteen Lakhs only) apart from what was awarded by the NCDRC. Therefore, apart from the refund of the entire amount deposited by the appellant @ 9% interest per annum from 11.07.2020 till the date of refund, the ADA is directed to pay an additional amount of Rs. 15,00,000/- (Fifteen Lakhs only) to the appellant.
 

The entire amount should be rendered to the appellant within three months of this order. We also order the ADA to return the non-judicial stamp worth Rs. 3,99,100/- back to the appellant.

24. Furthermore, we refrain from imposing any exemplary costs on either party, recognizing that both have contributed to the situation at hand. It is also to be noted that the ADA, being a civic body tasked with serving the public and operating on a non-profit basis, should not be unduly penalized in a manner that could impede its functioning.

25. The Civil Appeals 2809-2810 of 2024 are disposed of accordingly.

26. The appeal filed by the ADA i.e. Civil Appeal No.6344 of 2024 stands dismissed, as its primary arguments regarding both limitation and pecuniary jurisdiction are found to be without merit."

Download order dated 6th September 2024 in DHARMENDRA SHARMA. vs AGRA DEVELOPMENT AUTHORITY, Civil Appeal Nos. 2809-2810 of 2024

 

Latest Supreme Court Judgments

Stamp Duty should be paid while registering Agreement to Sell which shows transfer of physical possession of property, Supreme Court, Appeal dismissed
Prosecution failed to place any evidence to prove suppression of material information, accused acquitted by the Supreme Court, in a case of holding a second passport
Supreme Court set aside the Judgment of High Court acquitting the accused who stored and watched child pornography on mobile phone.
Independent review by authority recommending and granting sanction are necessary aspects of compliance with Section 45 of the UAPA
Accused in a dowry death case acquitted by Supreme Court as necessary ingredients have not been proved beyond reasonable doubt .
Supreme Court granted bail Mr. Arvind Kejriwal in CBI case in connection with the alleged liquor excise policy case filed by CBI. Separate Judgment.
FIR against illegal sex determination test quashed by supreme court as there was nothing to connect the accused with the offence except search and seizure documents
Election Petition properly filed with particulars of corrupt practices require trial. Appeal against rejection of application under order VII Rule 11 dismissed by Supreme Court
High Court was not right in dismissing the writ petitions on the ground of delay and laches - Supreme Court
Resignation withdrawn before delayed acceptance. Supreme Court directed for reinstatement of employee.
Criminal Appeal allowed and detention order quashed by the Supreme Court on the ground of delay in deciding representation given by the accused to detaining authorities
Offer of Possession without completion certificate is not valid Supreme Court orders full refund of amount paid by consumer with 9% interest p.a. and Rs. 15 lakh compensation
Supreme Court orders complete and fair investigation by CBI into the death of Assistant District Prosecution Officer, Dantewada
Lawyer did not conduct proper cross-examination is no ground to recall witness under 311 CrPC, Supreme Court.

 

Supreme Court order dated 20.08.2024, in Kolkatta rape and murder case of doctor, to formulate protocols governing issues in the health care sector and protection of Doctors and Healthcare staff
Writ Petition has been filed in the Supreme Court seeking direction for ensuring protection for doctors and health care professionals, Improved working conditions and safety working environment