Power to take possession of land to be acquired is defined under section 38 of Land Acquisition Act 2013. Provisions under this Section is:
Section 38 of Land Acquisition Act 2013 "Power to take possession of land to be acquired"
(1) The Collector shall take possession of land after ensuring that fill payment of compensation as well as rehabilitation and resettlement entitlements are paid or tendered to the entitled persons within a period of three months for the compensation and a period of six months for the monetary part of rehabilitation and resettlement entitlements listed in the Second Schedule commencing from the date of the award made under section 30:
Provided that the components of the Rehabilitation and Resettlement Package in the Second and Third Schedules that relate to infrastructural entitlements shall be provided within a period of eighteen months from the date of the award:
Provided further that in case of acquisition of land for irrigation or hydel project, being a public purpose, the rehabilitation and resettlement shall be completed six months prior to submergence of the lands acquired.
(2) The Collector shall be responsible for ensuring that the rehabilitation and resettlement process is completed in all its aspects before displacing the affected families.
Section 21 Notice to persons interested
Section 22 Power to require and enforce tile making of statements as to names and interests
Section 23 Enquiry and Land Acquisition award by collector
Section 25 Period within which an award shall be made
Section 26 Determination of Market Value of land by collector
Section 27 Determination of amount of compensation
Section 28 Parameters to be considered by Collector for determination of award
Section 29 Determination of value of things attached to land or building
Section 31 Rehabilitation and Resettlement Award for affected families by Collector
Section 32 Provision of infrastructural amenities in resettlement area
Section 33 Corrections to awards by collector
Section 35 Power to summon and enforce attendance of witness and production of documents
Section 36 Power to call for records
Section 37 Awards of collector when to be final
Section 38 Power to take possession of land to be acquired
Section 39 Additional compensation in case of multiple displacements
Section 40 Special powers in case of urgency to acquire land in certain cases
Section 41 Special Provision for Scheduled Castes and Scheduled Tribes