Lapse of Social Impact Assessment report is defined under section 14 of Land Acquisition Act 2013. Provisions under this Section is:
Section 14 of Land Acquisition Act 2013 "Lapse of Social Impact Assessment report"
Where a preliminary notification under section 11 is not
issued within twelve
months from the date of appraisal of the Social Impact
Assessment report submitted by the Expert Group under
section 7, then, such report shall be deemed to have lapsed
and a fresh Social Impact Assessment shall be required to be
undertaken prior to acquisition proceedings under section
11:
Provided that the appropriate Government, shall have the power to extend the period of twelve months, if in its opinion circumstances exist justifying the same:
Provided further that any such decision to extend the period shall be recorded in writing and the same shall be notified and be uploaded on the website of the authority concerned.
Section 4 Preparation of Social Impact Assessment Study
Section 5 Public hearing of Social Impact Assessment
Section 6 Publication of Social Impact Assessment Study
Section 7 Appraisal of Social Impact Assessment Report by an Expert Group
Section 9 Exemption from Social Impact Assessment
Section 10 Special Provision to safeguard Food Security
Section 11 Publication of preliminary notification and power of officers thereupon
Section 12 Preliminary survey of land and power of officers to carry out survey
Section 14 Lapse of Social Impact Assessment report
Section 16 Preparation of rehabilitation and resettlement scheme by the administrator
Section 17 Review of rehabilitation and resettlement scheme
Section 18 Approved rehabilitation and resettlement scheme to be made public
Section 19 Publication of declaration and summary of Rehabilitation and Resettlement
Section 20 Land to be marked out measured and planned including marking of specific areas